A JOINT RESOLUTION OF THE COUNTY OF MESA AND THE CITY OF GRAND JUNCTION CONCERNING ADOPTION OF ADMINISTRATIVE AMENDMENT TO THE FISCAL YEAR 2001-2006 TRANSPORTATION IMPROVEMENT PROGRAM
WHEREAS, The City and County have been designated by the Governor
as the Metropolitan Planning Organization for the Grand
Junction/Mesa County Urbanized Area; and
WHEREAS, Part 2 of Article 1 of Title 29, Colorado Revised
Statutes authorizes the parties to contract with one
another to make the most efficient and effective use of
their powers and responsibilities; and
WHEREAS, The City and County realize the importance of both short
and long range planning in the development of an
efficient transportation system, and are both aware that
it is the responsibility of the Metropolitan Planning
Organization to perform those planning functions; and
WHEREAS, The City and County, in their performance of those
planning functions for the Urbanized Area, wish to use
Federal Highway Administration transportation planning
funds in coordination with the Colorado Department of
Transportation;
NOW, THEREFORE, BE IT JOINTLY RESOLVED BY THE BOARD OF COUNTY
COMMISSIONERS OF THE COUNTY OF MESA, COLORADO AND THE CITY COUNCIL OF THE CITY OF GRAND JUNCTION, COLORADO:
That the Administrative Amendment to the Fiscal Year 2001-2006 Transportation Improvement Plan, hereunto attached, is adopted by the Board of County Commissioners of the County of Mesa, Colorado on March 19, 2001, and by the City Council of the City of Grand Junction, Colorado on March 21, 2001.
CITY OF GRAND JUNCTION COUNTY OF MESA
/s/ Gene Kinsey _ /s/ Kathryn H. Hall_______________
Mayor Chair of the Board
Grand Junction City Council Mesa County Board of Commissioners
21st day of March, 2000 19th day of March, 2000
Attest: Attest:
/s/ Stephanie Nye ______ /s/ Monika Todd by Roberta Raley, Deputy
City Clerk County Clerk
TRANSPORTATION IMPROVEMENT PROGRAM
ADMINISTRATIVE AMENDMENT
FOR THE
GRAND JUNCTION/MESA COUNTY URBANIZED AREA
FEBRUARY 23, 2001
PREPARED BY THE
MESA COUNTY
REGIONAL TRANSPORTATION PLANNING OFFICE
IN COOPERATION WITH THE
COLORADO DEPARTMENT OF TRANSPORTATION
DIVISION OF TRANSPORTATION DEVELOPMENT
CITY OF GRAND JUNCTION
MESA COUNTY
AND THE
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
FEDERAL TRANSIT ADMINISTRATION
INTRODUCTION
The Transportation Improvement Program (TIP) is a six-year capital improvement program for the urbanized area of Grand Junction and Mesa County. The Grand Junction/Mesa County Metropolitan Planning Organization (MPO) is charged with carrying out continuing, comprehensive and cooperative transportation planning by:
• Coordinating projects in the urbanized area initiated by individual City, County, and State agencies;
• Defining the costs of these projects and the available financial resources;
• Prioritizing the projects to make the best use of available resources.
The TIP serves not only the need in this area for an efficient transportation system, but also satisfies regulations jointly issued by the Federal Transit Administration (FTA) and Federal Highway Administration (FHwA), regarding the content and purpose of the program. Amendments to an approved TIP are necessary (as per Section F, paragraphs 2a, 2b, and 2c of the Grand Junction Urbanized Area Memorandum of Agreement dated July 2, 1984) to maintain federal funding for highways and streets within the planning area, and for federal assistance on transit programs. It is developed by the Mesa County Regional Transportation Planning Office (RTPO) acting as the MPO.
CONTENTS
The TIP shall contain all federally funded transportation projects in the urbanized area initiated by Mesa County, Grand Junction or by the Colorado Department of Transportation (CDOT). It is also necessary to include operating and/or capital grants from the U.S. Department of Transportation's Federal Transit Administration to agencies (public or private) in the urbanized area. The urbanized area (or Federal Aid Urban Boundary) is defined by the boundary of the Metropolitan Planning Organization (MPO).
In 1985 the City and the County began a two-year cycle for sharing of Small Urban Program funds. This allows the money to be used more effectively on larger projects. Annual adjustments of funds were made as required with input from the City, County and CDOT. Beginning in 1992, the City and County began to apply for these funds jointly and coordinate their planned improvements in such a way as to maximize the efficiency of the funds expended.
FORMAT
Format for the TIP is specified by federal and state requirements. Projects are broken out by:
1. Funding Source - (STP, FTA, etc.)
2. Priority - The projects are listed by priority in the first year of the program.
Each project must identify the location, description, responsible agency, general purpose, whether the project has received or will receive federal/state funding beyond the program period, and the breakdown of funding by year and by source. This format is standardized by CDOT for all urbanized areas. The general purpose relates to whether the project either furthers the goals of the State of Colorado=s 20-year Transportation Plan.
PROCESS
The projects in the TIP are originally proposed for inclusion by the implementing agencies. Projects are then considered by members of the Transportation Technical Advisory Committee (TTAC), which is composed of representatives from all public agencies involved in construction or operation of transportation systems in the Grand Junction Urbanized area.
After review of the program, the TIP is forwarded to the Transportation Policy Advisory Committee (TPAC), composed of local representatives from the Grand Junction City Council, the Mesa County Board of Commissioners, the Federal Highway Administration (FHwA), State Air Quality Control Commission and the local Transportation Commissioner and the. The TPAC may refer the program back to the TTAC or endorse the program and place it before the Mesa County Commissioners and the Grand Junction City Council for their approval. The Council and the County Commissioners will either approve the program or refer it back to the TPAC for consideration. A copy of the final document is sent to CDOT for review and approval.
Finally, the TIP is sent to the Governor for his approval and forwarded to the Federal Highway Administration and the Environmental Protection Agency for concurrence and/or comments. The FTA Region VIII office in Denver, Colorado also receives a copy of the approved document.
Amendments to the TIP are required when there are major changes in the cost of a project or when there are additions to or deletions of projects within the TIP. These are approved in the same manner as the program. Flexibility is required to allow for construction cost changes or for the allocation of additional Federal or State funds.
TRANSPORTATION IMPROVEMENT PROGRAM
ADMINISTRATIVE AMENDMENTS
FY 2001-2006
TRANSIT
Location: Mesa County
Project Description: Administrative amendment reflecting additional FTA Section 5309 funding for capital costs associated with the Historic Intermodal Plaza in FY 2002.
Responsible Government: Mesa County
Past Funding: Y Future Funding: Y Long Range: Y TSM: N
CAPITAL LINE ITEM
Budget Year |
|
2002 prior TIP total |
|
2002 proposed increase |
|
2002 amended TIP total |
Federal |
|
$224,000.00 |
|
$400,000.00 |
|
$624,000.00 |
Local |
|
56,000.00 |
|
100,000.00 |
|
156,000.00 |
TOTAL |
|
$280,000.00 |
|
$500,000.00 |
|
$780,000.00 |
- - End of Administrative Amendments - -
FY 2001 thru 2006 Transportation Improvement Program (TIP) Prior to Amendment Grand Junction / Mesa County MPO |
Route | Beg. | Length | Project | County | Project | Improvement Type | Funding | Funds | FY 2001 | FY 2002 | FY 2003 | FY 2001-03 | FY 2004-06 | Future |
# | M.P. | Miles | Description/Location | Sponsor | $ | $ | $ | $ | $ | $ | ||||
Transit | ||||||||||||||
Mesa County - Operating Assistance for Transit 50/50 | Mesa | Mesa | Operating | Total | FTA | 1,563 | 493 | 493 | 2,549 | 1,479 | 0 | |||
Federal | 5307 | 782 | 247 | 247 | 1,276 | 741 | ||||||||
Local | 781 | 246 | 246 | 1,273 | 738 | |||||||||
Mesa County - Capital Acquisition @ 80/20 match | Mesa | Mesa | Capital | Total | FTA | 50 | 277 | 237 | 564 | 711 | 0 | |||
Capital improvements for transit stops in 2002 | Federal | 5307 | 40 | 222 | 190 | 452 | 570 | |||||||
Project administration costs in 2001-2002 | Local | 10 | 55 | 47 | 112 | 141 | ||||||||
Mesa County - Associated Capital Maintenance | Mesa | Mesa | ACM | Total | FTA | 35 | 25 | 25 | 85 | 75 | 0 | |||
Federal | 5307 | 28 | 20 | 20 | 68 | 60 | ||||||||
Local | 7 | 5 | 5 | 17 | 15 | |||||||||
Mesa County - Capital Cost of Contracting | Mesa | Mesa | Capital | Total | FTA | 195 | 123 | 123 | 441 | 369 | 0 | |||
Federal | 5307 | 156 | 98 | 98 | 352 | 294 | ||||||||
Local | 39 | 25 | 25 | 89 | 75 | |||||||||
TOTAL - TRANSIT | 1,843 | 918 | 878 | 3,639 | 2,634 | 0 |
FY 2001 thru 2006 Transportation Improvement Program (TIP) Administrative Amendment |
Route | Beg. | Length | Project | County | Project | Improvement Type | Funding | Funds | FY 2001 | FY 2002 | FY 2003 | FY 2001-03 | FY 2004-06 | Future |
# | M.P. | Miles | Description/Location | Sponsor | $ | $ | $ | $ | $ | $ | ||||
Transit | ||||||||||||||
Mesa County - Operating Assistance for Transit 50/50 | Mesa | Mesa | Operating | Total | FTA | 1,563 | 493 | 493 | 2,549 | 1,479 | 0 | |||
Federal | 5307 | 782 | 247 | 247 | 1,276 | 741 | ||||||||
Local | 781 | 246 | 246 | 1,273 | 738 | |||||||||
Mesa County - Capital Acquisition @ 80/20 match | Mesa | Mesa | Capital | Total | FTA | 50 | 277 | 237 | 564 | 711 | 0 | |||
Capital improvements for transit stops in 2002 | Federal | 5307 | 40 | 222 | 190 | 452 | 570 | |||||||
Project administration costs in 2001-2002 | Local | 10 | 55 | 47 | 112 | 141 | ||||||||
Mesa County - Associated Capital Maintenance | Mesa | Mesa | ACM | Total | FTA | 35 | 25 | 25 | 85 | 75 | 0 | |||
Federal | 5307 | 28 | 20 | 20 | 68 | 60 | ||||||||
Local | 7 | 5 | 5 | 17 | 15 | |||||||||
Capital Improvements to the Historic Intermodal Plaza | Mesa | Mesa | Capital | Total | FTA | 0 | 500 | 0 | 500 | 0 | 0 | |||
Federal | 5309 | 0 | 400 | 0 | 400 | 0 | ||||||||
Local | 0 | 100 | 0 | 100 | 0 | |||||||||
Mesa County - Capital Cost of Contracting | Mesa | Mesa | Capital | Total | FTA | 195 | 123 | 123 | 441 | 369 | 0 | |||
Federal | 5307 | 156 | 98 | 98 | 352 | 294 | ||||||||
Local | 39 | 25 | 25 | 89 | 75 | |||||||||
TOTAL - TRANSIT | 1,843 | 1,418 | 878 | 4,139 | 2,634 | 0 |